Current Status

Last reviewed: November 15, 2026

The project has moved from environmental review into design. Caltrans approved Alternative F, a tunnel bypass east of the existing highway, and completed the Final Environmental Impact Report/Environmental Impact Statement, the federal Record of Decision, and the Project Report in 2026. The Project Report was signed on July 15, 2026. Official document library

What is settled

What is not settled

Work happening now

Geotechnical investigations are scheduled through January 31, 2027. This is design-support work, not tunnel construction. Travelers may encounter traffic control near active work areas. Current field-work notice

Current Status

The September 2026 update reports completion of the Final EIR/EIS and Final Section 4(f) Evaluation, execution of the National Historic Preservation Act Section 106 Memorandum of Agreement, completion of procurement for the final design consultant, and continuing procurement for independent technical support services.

Current Work, Travel Information, and Participation

The update says the next phase of geotechnical exploration was being prepared to start in September 2026. It also lists permittee-responsible mitigation connected with the geotechnical work and coordination with Redwood National and State Parks.

Cost, Funding, and Schedule

The update says the California Transportation Commission approved Caltrans District 1's request to allocate funds for the design and right-of-way support phases at its August 21, 2026 meeting.

Current Status

Caltrans announced that the Project Approval and Environmental Document phase was complete and the project had advanced to design. The approved concept is an approximately 6,000-foot tunnel east of the current highway. Detailed design will further develop the tunnel, portals, connecting road, bridge, drainage, safety systems, and operations and maintenance facilities.

Cost, Funding, and Schedule

Caltrans said current California Transportation Commission materials identified about $225 million for design and right-of-way support and estimated construction at $2.5 billion to $3.5 billion. Construction funding had not been secured. Caltrans expected to pursue a mix of federal, state, and financing opportunities during design. Construction was anticipated to begin in 2031.

Communities, Businesses, and Road Users

Caltrans described the road as a lifeline for residents, emergency responders, businesses, freight, and tourism. A long-term closure would force an approximately eight-hour detour through inland Northern California and Oregon. Caltrans said a specific construction-job estimate had not yet been developed.

Tribal Nations and Cultural Resources

Caltrans said it was working with local Tribes on Native American hiring and workforce development, including coordination with Yurok Construction Corporation and exploration of educational opportunities for Tribal youth.

Current Status and How to Stay Current

As of November 2026: Final environmental document and Project Report approved; preferred alternative selected; design phase underway (geotechnical investigations on schedule); CTC design/ROW funding allocated; construction funding still needed; open houses and advocacy continuing. Quarterly project updates, progress reports, and a full document library are published on the official site.

This summary reflects publicly available information through late 2026. New documents, design refinements, funding decisions, and mitigation details will continue to appear on the official site and in agency notices.

Caltrans selected Alternative F—a roughly 6,000-foot (1.1-mile) tunnel east of the existing highway—as the preferred alternative. It would be the longest tunnel in Caltrans history (longer than each of the twin Tom Lantos Tunnels at Devil’s Slide). The project is the largest and most complex ever for Caltrans District 1. As of late 2026, the Project Approval & Environmental Document (PA&ED) phase is complete, the final EIR/EIS is certified, and the project has advanced into the design phase. Construction is targeted to begin in 2031, contingent on funding.