Stakeholders and Decision-Making
Different groups have different roles. Collaboration does not erase legal authority or mean every participant agrees on every issue.
Lead agency and project owner
Caltrans District 1 leads project development and delivery. Caltrans is the CEQA lead agency and acts under federal assignment for NEPA. It approved the selected alternative and is responsible for design, procurement, funding strategy, mitigation commitments, and construction delivery.
Formal project Partners
The official partner group includes:
- Caltrans District 1
- California Department of Parks and Recreation
- National Park Service
- Green Diamond Resource Company
- Elk Valley Rancheria
- Pulikla Tribe of Yurok People
- Tolowa Dee-ni’ Nation
- Yurok Tribe
These organizations have land, resource, cultural, technical, or governmental responsibilities connected with the project area.
Broader stakeholder process
Congressman Jared Huffman's stakeholder group has included Tribal governments, Crescent City and county governments, transportation agencies, environmental organizations, law enforcement, local businesses, landowners, and elected offices. Working groups have addressed cultural resources, biology, mitigation, alternatives, and economic issues.
Public and regulatory checks
The project has also involved the California Transportation Commission, State Historic Preservation Office, US Fish and Wildlife Service, National Marine Fisheries Service, US Army Corps of Engineers, coastal and park authorities, and the public review processes required by CEQA and NEPA.