Selected Tunnel Project
Alternative F is the approved project concept. It realigns US 101 east of the current highway and carries the route through an approximately 6,000-foot (about 1.1-mile) tunnel that bypasses the most unstable slide area.
Official Caltrans concept map. The lines are approximate and do not show final design geometry. Select the image for the authoritative selected-alternative page.
Planned features
- One 12-foot travel lane in each direction
- Eight-foot shoulders
- A separated bicycle and pedestrian facility through the tunnel
- North and south portals and connecting roadway
- A bridge, drainage, safety, ventilation, and monitoring systems to be developed in final design
- An operations and maintenance center
The project is still in design. Published maps show an approximate alignment, not final portal, roadway, or facility geometry.
Why this option was selected
Caltrans says the tunnel offers the lowest long-term closure risk among the studied alternatives and reduces exposure to coastal erosion and the active landslide. It also concentrates surface disturbance around portals and approaches instead of rebuilding the full existing slide corridor.
Current estimate
The selected-alternative page gives a construction estimate of $2.7 billion in 2026 dollars and an anticipated construction duration of six to eight years. A later Caltrans design-phase announcement gives a broader current construction range of $2.5 billion to $3.5 billion. Both remain estimates subject to design, geotechnical findings, market conditions, mitigation, and funding. Selected alternative
Selected Tunnel Project
Alternative F is a major realignment east of the existing highway with an approximately one-mile underground tunnel and an operations and maintenance center. The tunnel is planned with one lane in each direction, eight-foot shoulders, and a separated bicycle/pedestrian facility. The map alignment is approximate and is not final design geometry.
Cost, Funding, and Schedule
Caltrans estimates construction at $2.7 billion in 2026 dollars and an anticipated construction duration of approximately six to eight years. The estimate includes construction, materials disposal, and mitigation.