Slides, Closures, and Repairs

The highway crosses a large, active landslide complex above the Pacific Ocean. Caltrans describes landslides as recurring one to three times per decade, with damage accelerating in recent years.

[image: Caltrans photograph of repaired pavement between Wilson Creek and the north end of Last Chance Grade]

Caltrans repair photograph. Select the image for the official project history and repair record.

Key events

Caltrans says the road is monitored and safe for public use, but continued movement means maintenance and emergency work will remain necessary until a permanent route is built. Project history Safety FAQ

Why This Corridor Matters

US 101 is a year-round route for commercial trucking and recreational travel. Caltrans says landslide repair projects since 1997 have cost more than $100 million. A major closure would disrupt residents, travelers, businesses, emergency access, freight, and tourism.

Slides, Closures, and Repairs

The project page says landslides typically occur one to three times per decade and damage has accelerated. Significant roadway damage followed storms in March 2011 and March 2012. Storm damage in 2017 temporarily removed the southbound lane near post mile 14.4. Emergency work after the winters of 2015, 2017, and 2018 used four contracts totaling $49 million and included replacing three damaged retaining walls and building three new walls. On February 15, 2021, about 40,000 cubic yards of rock and slide debris moved during a large storm, fully closing the highway; repair-related lane closures continued until the end of August 2021. In October 2023, retaining-wall construction was completed and two-way traffic resumed for the first time in about nine years.

Alternatives Studied

The Engineered Feasibility Study was completed in 2015. A Project Study Report followed in 2016. An April 2021 alternatives analysis carried Alternatives X and F forward for environmental review and recommended removing A1, A2, G1, G2, and L because they performed less well and had greater potential impacts.

Cost, Funding, and Schedule

The California Transportation Commission approved $5 million in May 2017 for preliminary geotechnical investigations and another $45 million in March 2019 for the environmental phase.

Landslides occur on average 1–3 times per decade. Caltrans has spent well over $100 million since 1997 (and substantial amounts earlier) on emergency repairs, retaining walls (more than two dozen), drainage, realignments, and maintenance. Notable recent issues include multi-year one-way traffic (roughly 2014–2023), a full multi-day closure in early 2021, and ongoing intermittent problems. A catastrophic long-term failure remains a major risk. There is no practical detour—only lengthy inland routes or unusable logging roads.

History of the Slides and Closures

A one-year full closure has been estimated to cost Del Norte County on the order of $1 billion (or regionally: hundreds of millions in travel costs and reduced business output, thousands of jobs). The road is monitored and kept open/safe for now, but repair costs are unsustainable and climate-driven storms are increasing risk.

The current alignment dates to the 1930s (after an earlier wagon trail). Engineers noted instability even during construction. Portions rest on active earthflows and fractured rock near the Cascadia Subduction Zone; over 200 historical and active landslides (deep-seated and shallow) have been mapped in the corridor. The road has shifted tens of feet horizontally and vertically since the 1930s, with movement accelerating in recent years (some sections moving several feet per year toward the ocean in places).