Cost, Funding, and Schedule

Cost estimates

MeasureCurrent public figureWhat it means
Selected Alternative F construction estimate$2.7 billion (2026 dollars)Point estimate on the selected-alternative page; includes construction, material disposal, and mitigation
Current construction range$2.5–$3.5 billionBroader range cited by Caltrans when the project entered design
Design-phase allocationAbout $218 millionCalifornia Transportation Commission allocation reported by Caltrans in August 2026
Design and right-of-way supportAbout $225 millionRounded/scoped figure in the project-specific Caltrans announcement

The two design figures come from different Caltrans announcements and should not be added together. They likely reflect rounding or scope differences.

Funding status

Design and right-of-way support are funded. Construction is not fully funded. Caltrans says it will pursue a mix of federal, state, and financing opportunities while design proceeds.

Potential schedule

These are planning dates, not guarantees. The official schedule assumes timely funding and approvals; funding gaps, design changes, permitting, subsurface conditions, procurement, or construction risk can move them. Official process and schedule Caltrans design-phase announcement

Cost, Funding, and Schedule

The official potential timeline places design and permitting in 2026–2031, construction in 2031–2038, and opening of the alternative route in 2039. Caltrans labels the timeline as potential and based on assumptions about selecting the most expensive, longest-duration alternative studied in 2021. Funding gaps or design and permitting changes can affect dates.

Slides, Closures, and Repairs

The schedule records community workshops and completion of the feasibility study in 2015, completion of the Project Study Report in 2016, preliminary geotechnical work and risk/economic/value studies in 2017–2018, and the environmental-document phase through 2026.

Cost, Funding, and Schedule

Caltrans reported that the California Transportation Commission approved approximately $218 million toward the design phase of the Last Chance Grade Tunnel Project. This is a design-phase allocation, not construction funding.

Current Status

The announcement identifies the project as the Last Chance Grade Tunnel Project on US 101 south of Crescent City in Del Norte County.

Cost, Schedule, and Funding