Cost, Funding, and Schedule
Cost estimates
| Measure | Current public figure | What it means |
|---|---|---|
| Selected Alternative F construction estimate | $2.7 billion (2026 dollars) | Point estimate on the selected-alternative page; includes construction, material disposal, and mitigation |
| Current construction range | $2.5–$3.5 billion | Broader range cited by Caltrans when the project entered design |
| Design-phase allocation | About $218 million | California Transportation Commission allocation reported by Caltrans in August 2026 |
| Design and right-of-way support | About $225 million | Rounded/scoped figure in the project-specific Caltrans announcement |
The two design figures come from different Caltrans announcements and should not be added together. They likely reflect rounding or scope differences.
Funding status
Design and right-of-way support are funded. Construction is not fully funded. Caltrans says it will pursue a mix of federal, state, and financing opportunities while design proceeds.
Potential schedule
- 2026–2031: detailed design, permitting, right of way, mitigation development, geotechnical investigation, and cost refinement
- 2031: currently anticipated construction start
- 2031–2038: potential construction period
- Around 2039: potential opening to traffic
These are planning dates, not guarantees. The official schedule assumes timely funding and approvals; funding gaps, design changes, permitting, subsurface conditions, procurement, or construction risk can move them. Official process and schedule Caltrans design-phase announcement
Cost, Funding, and Schedule
The official potential timeline places design and permitting in 2026–2031, construction in 2031–2038, and opening of the alternative route in 2039. Caltrans labels the timeline as potential and based on assumptions about selecting the most expensive, longest-duration alternative studied in 2021. Funding gaps or design and permitting changes can affect dates.
Slides, Closures, and Repairs
The schedule records community workshops and completion of the feasibility study in 2015, completion of the Project Study Report in 2016, preliminary geotechnical work and risk/economic/value studies in 2017–2018, and the environmental-document phase through 2026.
Cost, Funding, and Schedule
Caltrans reported that the California Transportation Commission approved approximately $218 million toward the design phase of the Last Chance Grade Tunnel Project. This is a design-phase allocation, not construction funding.
Current Status
The announcement identifies the project as the Last Chance Grade Tunnel Project on US 101 south of Crescent City in Del Norte County.
- Schedule: PA&ED complete (2026). Design, geotechnical work, permitting, and right-of-way ongoing through ~2031. Construction targeted to start 2031 (duration multi-year). Earlier high-level schedules projected possible opening in the mid-to-late 2030s depending on the alternative and funding continuity.
- Construction cost: Currently estimated in the $2.5–3.5 billion range (earlier figures around $2.1 billion in 2031 dollars). Escalation alone is estimated at ~$180 million per year of delay.
- Design / right-of-way support: ~$225 million (California Transportation Commission allocated ~$218 million in SHOPP funds in August 2026 for PS&E and ROW support).
- Funding: Design phase largely supported via state SHOPP. Construction funding is not yet secured; Caltrans is pursuing a mix of federal, state, and financing options. Historical work used emergency-relief and other sources. Local, state, and federal officials have urged continued advocacy.