Current Work, Travel Information, and Participation

Current field work

Caltrans is conducting geotechnical investigations along US 101 south of Crescent City, including locations in and near Redwood National and State Parks, through January 31, 2027. The work collects subsurface information for tunnel design. It is not tunnel construction.

Travelers and park visitors do not need to change plans solely because of this investigation. No trail or parking-area closures are planned for the investigation, but people may see or hear workers, equipment, temporary access work, and traffic control.

Before traveling

Follow the project

Participation

Public meetings, notices, and comment opportunities change by project phase. The formal environmental comment period is complete, but design, mitigation, workforce, construction-readiness, and local-business coordination continue. New opportunities should be verified against the official website rather than carried forward from an old flyer or meeting notice.

Current Work, Travel Information, and Participation

Caltrans says field investigations along US 101 south of Crescent City, including work in and near Redwood National and State Parks, are scheduled through January 31, 2027. The work gathers detailed subsurface information for tunnel design; it is not tunnel construction. No trail or parking closures are planned for this investigation, but travelers may encounter traffic control and may see or hear workers, equipment, and temporary-access-road activity. Caltrans directs travelers to QuickMap for near-real-time highway conditions and to District 1's weekly planned-work updates.

Cost, Funding, and Schedule

Caltrans continues to anticipate beginning tunnel construction in 2031.

Why This Corridor Matters

The page describes an approximately 449-mile detour taking about eight additional hours if a long-term closure forced travelers through inland Northern California and Oregon.